AFTER THE commissioning of the 272-km Udhampur-Srinagar-Baramulla Rail Link (USBRL), also called Kashmir Line, the Railways is now working on the extension of the key project.
Story continues below this ad
Minister for Railways Ashwini Vaishnaw on Friday told the Rajya Sabha that survey of the Baramulla-Uri new line (46 km) and Banihal-Baramulla doubling (118 km) has been completed and the Detailed Project Report (DPR) has been prepared. The projects are yet to be sanctioned. The Baramulla-Uri line will be an extension of the USBRL.

“After preparation of DPR, sanctioning of project requires consultation with various stakeholders, including state governments, and necessary approvals, appraisal of NITI Aayog, Ministry of Finance etc.,” said Vaishnaw in a written response in Rajya Sabha.
Story continues below this ad
Currently, two Vande Bharat trains are operational between Katra and Srinagar section of the project. Further, six pairs of DEMU/MEMU services are available for the Qazigund-Srinagar section and 5 pairs of DEMU/MEMU services are catering to the Srinagar-Baramulla section.
Vaishnaw said the commissioning of the project has helped farmers in transporting apples to different parts of the country.
Story continues below this ad
The Kashmir Line was one of the most difficult projects undertaken by the Indian Railways. Prime Minister Narendra Modi inaugurated the line on June 6. The complete 272-km stretch was constructed at the cost of Rs 43,780 crore, which includes 36 tunnels.
The trickiest stretch was the Katra-Banihal section, totalling 111 km. This includes India’s longest operational transportation tunnel, T-50, running to 12.77 km, the world’s highest railway arch bridge at 359 metres above the sea floor (the Chenab Bridge), and the first cable-stayed railway bridge (the Anji Bridge).
The idea to connect Kashmir with a railway line between Jammu and Srinagar was first conceived by Maharaja Pratap Singh in 1898. In 1905, he approved the construction of a narrow gauge (762-mm) railway line via Reasi.
Story continues below this ad
The then princely state of Jammu and Kashmir was later connected to the rail grid with a line between Jammu and Sialkot. But with the latter going to Pakistan following Partition, J&K rail line got disconnected with the rest of India.
While Jammu eventually got a train, it was in 1983 that the then Indira Gandhi-led Congress government laid the foundation stone for a Udhampur-Srinagar railway line. Work on the project gained momentum after Atal Bihari Vajpayee-led NDA government declared it a national project in 2002.
© The Indian Express Pvt Ltd
.